If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

A student government organization is selling Christmas trees as a fundraiser. On Friday, they sold 5 noble fir trees and 3 douglas fir trees for a total of $420
The Earth has four main seasons: winter, spring, summer, and fall. Which of the following is a cause of seasonal changes on Earth? The Earth rotates. The
Help pl0x, Algebra 1
PLEASE HELP I GIVE THANKS
does radiation need a phase of matter to travel with?
Solve the equation -10 + 3x + 5x = -56 ? ??
Do all your pet's offspring look the same? If no, then explain why they look different.
Which body tissue or organ contains the most mitochondria?
A recipe call for 2 cups of water for every 5 cups of flour. How many cups of water are needed for 1 cup of flour? A. 2 1/2 cups B. 2 cups C. 1/2 cup D. 2/5 cup
The length of a rectangle is 4 times its width and the perimeter is 150 feet. What is the width of the rectangle? A. 75 feet B. 30 feet C. 15 feet D. 60 fe